A contractor undertakes to complete a work in 250 days. He employs 300 workers for 50 days and they complete \(\frac{1}{2}\) of the work. He then reduces the number of workers to 100, who work for 120 days, after which there are 20 days of holidays. How many workers must be employed after holidays for the remaining period to complete the work on time?
1
74
2
68
3
50
4
80