A and B can complete a task in 40 days, B and C can complete it in 30 days while C and A can complete the same task together in 24 days. How many days will each of A, B and C take to complete the task individually?

1
48, 96 and 32
2
32, 48 and 96
3
60, 120 and 40
4
40, 120 and 60