railway RRB JE (CBT I + CBT II) Mock Test 2024 Industrial Engineering Production Planning and Inventory Control Inventory Control
Given an annual usage value of 400 units, the procurement cost is ₹20 per order, cost per piece is ₹100 and cost of carrying inventory is 10%. Calculate the EOQ.
1
60
2
40
3
30
4
50