Consider the following statements in respect of PERT and CPM:

1. PERT is event-oriented while CPM is activity-oriented.

2. PERT is probabilistic while CPM is deterministic.

3. Levelling and smoothing are the techniques related to resource scheduling in CPM.

Which of the statements given above are correct?

1
1, 2 and 3
2
1 and 2 only
3
2 and 3 only
4
1 and 3 only