railway RRB JE (CBT I + CBT II) Mock Test 2024 Industrial Engineering Production Planning and Inventory Control Material Requirement Planning (MRP)
Which of the following is not an input to the MRP system?
1
MPS (Master Production Schedule)
2
Bill of materials
3
Cost of materials
4
Inventory status