railway RRB JE (CBT I + CBT II) Mock Test 2024 Environmental Engineering Water Supply Distribution of Water
Damage in large pumping main due to water hammer can be prevented by:
1
Providing surge chamber near pump end
2
Providing surge tank near delivery end
3
Providing pipe with guniting on outer surface and coating in inner surface
4
Providing pump with sudden shut down