railway RRB JE (CBT I + CBT II) Mock Test 2024 Industrial Engineering Operations Research PERT and CPM
What is the total float of an activity for which
Earliest Start time ES = 5
Earliest Finish time EF = 15
Latest Start time LS = 35
Latest Finish time LF = 45
1
10
2
20
3
30
4
40