Five jobs need to be processed on a single machine. All the jobs are available for processing at time t = 0. Their respective processing times are given below.

Jobs

I

II

III

IV

V

Processing times (in minutes)

13

4

7

14

11

The mean completion time using the shortest processing time rule is _________ minutes.

1
9.8
2
24.2
3
49.0
4
121.0