If the level of canal bed and high flood level of river have the RL's of 110 m and 111.0 m respectively, then this type of cross drainage work is called
(Assume river bed level is lower than that of canal)

1
Level crossing
2
Super passage
3
Aqueduct
4
Siphon aqueduct