railway RRB JE (CBT I + CBT II) Mock Test 2024 Power Systems Economies of Power Generation Load Factor
An industrial consumer has a load pattern of 2000 kW at 0.8 lagging for 12 hours and 1000 kW at unity power factor for 12 hours. Its load factor is
1
0.6
2
0.8
3
0.5
4
0.75