The correct sequence of operations in production planning and control is
1
Routing-Scheduling-Dispatching-Follow up
2
Scheduling-Routing- Dispatching-Follow up
3
Dispatching-Routing-Scheduling- Follow up
4
Routing-Scheduling-Follow up-Dispatching