railway RRB JE (CBT I + CBT II) Mock Test 2024 Industrial Engineering Production Planning and Inventory Control Inventory Control
A company uses 2555 units of an item annually. Delivery lead time is 8 days. The reorder point (in number of units) to achieve optimum inventory is
1
7
2
8
3
56
4
60