railway RRB JE (CBT I + CBT II) Mock Test 2024 Construction Materials and Management Building Component
While laying out circular structures like wells or tanks, which of the following techniques ensures accuracy?
1
Swing method with tape
2
Bowstring method
3
Offset with cross staff
4
Chord and segmental method