Rahul can do a piece of work in 20 days whereas Rohan can do the same work in 30 days. Both started the work together and worked for 6 days with full efficiency, and in the next 6 days with half of their efficiencies. In how many days will the remaining work be finished if both work with their full efficiencies for the remaining period?

1
7 days
2
5 days
3
10 days
4
3 days