If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do it in 12 days, doing the work together they receive Rs. 5500. What is B’s share in that amount?

1
Rs. 1200
2
Rs. 1400
3
Rs. 1500
4
Rs. 1600