SSC SSC JE Electrical 2025 Mock Test Series (Paper 1 & Paper 2) Power Systems Economies of Power Generation Demand Factor
An apartment complex consists of 15 apartments, each with a peak demand of 8 kW. The maximum system demand recorded is 60 kW. What is the diversity factor?
1
0.5
2
3
3
1.5
4
2