P and Q can do a piece of work in 15 days and 20 days respectively. They work for 5 days and P left then in how many days Q alone can finish the remaining work?

1
\(8\frac{1}{3}\) days
2
\(7\frac{1}{3}\) days
3
\(8\frac{1}{2}\) days
4
8 days