A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

1
120 / 13 days
2
480 / 13 days
3
240 / 13 days
4
960 / 13 days