SSC SSC JE Electrical 2025 Mock Test Series (Paper 1 & Paper 2) Power Systems Economies of Power Generation
A system having connected load of 80 kW, peak load of 60 kW. base load of 30 kW and average load of 48 kW, will have a load factor of
1
40%
2
50%
3
60%
4
80%