the detail dimensions of each section of a half-sectional plan of an RCC slab culvert with right angled wing walls is given below. What is the total quantity of earthwork in excavation per meter span?

Section  Length (m) for each section Breadth (m) for each section Helgh/Depth (m) for each section
Abutments  5.10  0.70  2.60 
Wing Walls 1.20  0.70  0.60 

1
2.646 cu. m.
2
5.252 cu. m.
3
6.300 cu. m.
4
10.29 cu. m.
5