Teaching HPSC Lecturer (Technical) Mock Test 2024 Construction Materials and Management Construction Management
In PWD contracts, what is the primary purpose of a 'time-extension clause'?
1
To allow the contractor to renegotiate the contract terms
2
To extend the project timeline without incurring penalties
3
To reduce the scope of work under certain conditions
4
To request additional funds for unforeseen work
5
Question Not Attempted