Which of the following is NOT correct critical path method (CPM) used in Project scheduling?

1
The path with the longest time sequence the critical path.
2
For each activity earliest start time and latest start time are computed.
3
The length of the critical path determines the minimum time in which the entire project can be completed.
4
The path with the shortest time sequence is the critical path.
5
Question Not Attempted