Teaching HPSC Lecturer (Technical) Mock Test 2024 Construction Materials and Management Project Planning PERT
PERT calculations yield a project length of 70 weeks with a variance of 9 weeks. The number of weeks required to complete the project with a probability of 95% (probability factor for 95% = 1·647) is
1
73.94 weeks
2
74.94 weeks
3
75.94 weeks
4
76.94 weeks
5
Question Not Attempted