Teaching HPSC Lecturer (Technical) Mock Test 2024 Construction Materials and Management Project Planning PERT
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
1
4 days
2
6 days
3
10 days
4
16 days
5
Question Not Attempted