PERT Analysis is based on :

(i) Optimistic time

(ii) Most likely time

(iii) Pessimistic time

The correct answer is -

1
only (i)
2
only (ii)
3
only (i) and (ii)
4
(i), (ii) and (iii)
5
Question Not Attempted