Teaching HPSC Lecturer (Technical) Mock Test 2024 Construction Materials and Management Project Planning CPM
In critical path method of construction planning, free float can be
1. greater than total float
2. greater than independent float
3. equal to total float
4. less than independent float.
Of these statements,
1
only 1 and 4 are correct
2
only 2 and 3 are correct
3
only 2 and 4 are correct
4
only 1 and 2 are correct
5
Question Not Attempted