SSC SSC JE Civil 2025 Mock Test Series (Paper 1 & Paper 2) Construction Materials and Management Project Planning PERT
The area under β- distribution curve is divided into two equal parts by
1
Most likely time
2
Expected time
3
Optimistic time
4
Pessimistic time