SSC Delhi Police MTS (Civilian) Mock Test Series Quantitative Aptitude Time and Work Work Efficiency
A, B and C individually can do a work in 36 days, 60 days and 45 days, respectively. If they start working together, then the number of days required to finish the work is:
1
8
2
16
3
30
4
15