A fill having a volume of 15000 m3 is to be constructed at a void ratio of 0.5. The borrow pit solid has a void ratio of 1.5. The volume of soil required (in cubic meters) to be excavated from the borrow pit will be:

1
18750
2
20000
3
25000
4
75000