SSC SSC JE Civil 2025 Mock Test Series (Paper 1 & Paper 2) Estimating, Cost and Valuation Measurement
Calculate the amount required for cement to construct 1 m3 of RCC beam in 1 : 2 : 4 proportion with an addition of 40% voids in the concrete.Take ₹400 per bag of cement.
1
₹2,400
2
₹2,000
3
₹2,200
4
₹2,600