SSC SSC JE Civil 2025 Mock Test Series (Paper 1 & Paper 2) Estimating, Cost and Valuation Measurement
In case of unsymmetrical wall, no advantage may be claimed by ______ over other method of estimating building works.
1
Centre line method
2
Crossing method
3
Out to out and in to in method
4
Long and short wall