Teaching Jharkhand (JSSC) PRT (1 to 5) Mock Test 2023 Quantitative Aptitude Time and Work Work Efficiency
The working efficiency of A and B is 9 : 2. If A and B can complete the work in 8 days, then find the time taken by B to complete the work.
1
32 days
2
44 days
3
22 days
4
16 days