Teaching EMRS Accountant Mock Test 2023 Industrial Engineering Production Planning and Inventory Control Inventory Control
The expected demand for a product is 150 per day. The lead time is 10 days. An order is placed when the inventory falls to 4000 units. The safety stock is
1
1500 units
2
2500 units
3
3000 units
4
4000 units