Match the following:
| List I | List II | ||
|---|---|---|---|
| Techniques | Uses | ||
| I | PERT | A |
show the duration of activities in a project |
| II | Gantt Chart | B | useful for non-repetitive and complex projects in which time estimates are uncertain. |
| III | CPM | C |
best utilized for repetitive and non-complex projects when the time estimates can be made with some measure of certainty |
1
I-C, II-A, III-B
2
I-B, II-A, III-C
3
I-A, II-B, III-C
4
I-A, II-C, III-B