SSC SSC Selection Post (Phase 13) 2025 Mock Test Quantitative Aptitude Time and Work Work Efficiency
Rajeshwar can do a piece of work in 12 days, Vikram in 6 days and Tiger in 15 days. They all start the work together, but Rajeshwar leaves after 2 days and Vikram leaves 3 days before the work is completed. In how many days is the work completed?
1
\(5 \frac{4}{7}\)
2
\(5 \frac{5}{7}\)
3
\(5 \frac{3}{7}\)
4
\(5 \frac{6}{7}\)