Teaching UGC NET Mock Test Series 2025 (Paper 1 & 2) Industrial Engineering Operations Research PERT and CPM
A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is
1
3
2
9
3
81
4
27