The following statements relate to project network. Choose the correct code for the statements being correct or incorrect.

Statement I: An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.

Statement II : The activities in a critical path can be preponed or postponed.

1
Both the statements I and II are correct.
2
Both the statements I and II are incorrect.
3
Statement II is correct, but I is incorrect.
4
Statement I is correct, but II is incorrect.