Match List I with List II
|
LIST I (Project Network concepts) |
LIST II (Underlying meaning) |
||
| A. | Crashing an activity | I. | Length of the longest path through the project network |
| B. | Project Network | II. | It shows the time and cost when the activity is fully crashed |
| C. | Critical path | III. | It consists of a number of nodes and a number of arcs that connects two different nodes |
| D. | Crash point | IV. | Taking special (costly) measures to reduce the duration of an activity below its normal value |
Choose the correct answer from the options given below:
1
A - II, B - IV, C - III, D - I
2
A - IV, B - III, C - I, D - II
3
A - IV, B - III, C - II, D - I
4
A - III, B - I, C - IV, D - II