Arrange the Project Life Cycle phase in proper sequence from starting to end.
A. Definition phase
B. Conception phase
C. Implementation phase
D. Planning and organizing phase
E. Project clean-up phase
Choose the correct answer from the options given below:
1
A, B, D, E, C
2
B, A, D, C, E
3
B, A, C, D, E
4
E, A, C, D, B