Match the 5 CMM Maturity levels/CMMI staged representations in List- I with their characterizations in List-II :

 

List – I

 

List – II

(a)

Initial

(i)

Processes are improved quantitatively and continually.

(b)

Repeatable

(ii)

The plan for a project comes from a template for plans.

(c)

Defined

(iii)

The plan uses processes that can be measured

quantitatively.

(d)

Managed

(iv)

There may not exist a plan or it may be abandoned.

(e)

Optimizing

(v)

There’s a plan and people stick to it.

1
(a) – (iv), (b) – (v), (c) – (i), (d) – (iii), (e) – (ii)
2
(a) – (i), (b) – (ii), (c) – (iv), (d) – (v), (e) – (iii)
3
(a) – (v), (b) – (iv), (c) – (ii), (d) – (iii), (e) – (i)
4
(a) – (iv), (b) – (v), (c) – (ii), (d) – (iii), (e) – (i)