Identify the correct statements from the following regarding spiral model.

A. Spiral model is an incremental process model.

B. Spiral model is a risk - driven process mode.

C. Spiral model is an acyclic balancing approach.

D. Spiral model involves a set of anchor point milestone.

Choose the correct answer from the options given below:

1
A & B Only
2
B & C Only
3
A & D Only
4
B & D Only