Arrange the steps of project life cycle in sequence
A. Formation of project
B. Implementation
C. Identification of idea
D. Completion and operation
E. Feasibility analysis and finalization
Choose the correct answer from the options given below:
1
A, C, D, E, B
2
C, A, E, B, D
3
B, A, E, C, D
4
D, C, A, B, E