Which among the following are correct statements for the components of Critical Path Model (CPM)?
A. Events are represented by arrows.
B. The Earliest Start Time is the soonest time that an event can begin.
C. The Latest Start Time is calculated by working from the end of the diagram with the total time and subtracting the activity time from that.
D. Slack Event Time is the actual engagement time in an event.
E. The Slack Activity Time at node one should be zero.
Choose the correct answer from the options given below
1
B, C & E only
2
A, D & E Only
3
C, D & A Only
4
A, B & C Only