Suppose that jobs arrive according to the following schedule :                                                 

Process  Arrival time     Run time
A 12
3 7
6 2
D 8 5
E 9 2
F 12 12

Now give the sequence of the processes as they gets share of CPU if the scheduler used is Shortest Remaining Time First.

1
A,B,C,B,E,D,B,A,F
2
A,B,C,B,E,B,D,B,A,F
3
A,B,C,B,E,B,D,A,F
4
A,B,C,B,B,B,E,D,A,F