A construction company hired 1000 persons to construct a building in 77 days but the company realized after 44 days, 40% of the work had been finished. To complete the work on the scheduled time how many persons company has to increase ?

1
2000
2
4000
3
1000
4
3000
5
5000

Sponsored

hivanix.in

Visit

This quiz is brought to you by hivanix.in

🌐 Web App Development

Quick Navigation