Swimming Pool Contractor takes up a project to build a well furnished pool in 300 days with 160 workers. After 180 days of starting of project he notices 75% of the work is done. How many workers should he unemployee so that construction work still completes in 300 days.

1
160
2
80
3
100
4
120
5
60