Directions: The data below represents the number of people required for various project to be completed in different number of days. Use this information to answer the question asked.

Project

Situation I

Situation II

Number of Workers

Days Required

Number of Workers

Days Required

P1

x

(x + 5)

(x – 5)

(x + 15)

P2

y

(y + 10)

40

(y – 5)

P3

50

z

80

(y – 10)

P4

y

(z + 9)

(x + 16.25)

z

If 0.4x people work on project P2 for starting 10 days and then 0.8y people join the project with them after 10 days, how many days will it take to complete project P2? (if y < 15)

1
30 days
2
20 days
3
40 days
4
25 days
5
None of these