30 men can complete a work in 12 days. After 6 days, 24 more men joined them. How many days will they now take to complete the remaining work?
1
\(3\frac{1}{3}\) days
2
\(3\frac{2}{3}\) days
3
\(3\frac{1}{2}\) days
4
\(2\frac{1}{3}\) days
30 men can complete a work in 12 days. After 6 days, 24 more men joined them. How many days will they now take to complete the remaining work?