engineering recuitment OSSC Combined Technical Services (ଓଡିଶା) Mock Test 2023-24 Data Interpretation Pie Chart
Comprehension Passage
Direction: Refer to the pie chart given below.
The following pie charts show distribution of expense to construct a building. Total cost of construction is Rs 900000.
ଇଟା, ବାଲି ଏବଂ ସିମେଣ୍ଟରେ ଖର୍ଚ୍ଚ ହୋଇଥିବା ମୋଟ ପରିମାଣ କେତେ ହେବ ନିରୂପଣ କର ।
1
2,70,000 ଟଙ୍କା
2
5,40,000 ଟଙ୍କା
3
1,80,000 ଟଙ୍କା
4
3,60,000 ଟଙ୍କା