engineering recuitment OSSC Combined Technical Services (ଓଡିଶା) Mock Test 2023-24 Data Interpretation Pie Chart
Comprehension Passage
Direction: Refer to the pie chart given below.
The following pie charts show distribution of expense to construct a building. Total cost of construction is Rs 900000.
ಕಾರ್ಮಿಕರಿಗೆ ಖರ್ಚು ಮಾಡಿದ ಮೊತ್ತ ಎಷ್ಟು?
1
ರೂ. 1,80,000
2
ರೂ. 5,40,000
3
ರೂ. 3,60,000
4
ರೂ. 2,70,000